International Journal of Engineering Technology and Construction, 2024, 5(1); doi: 10.38007/IJETC.2024.050101.

Research on Assembly Time for Steel Girder

Author(s)

Zhansheng Lin, Jin Li, Tongjun Duan, Ranran Hu

Corresponding Author:
Zhansheng Lin
Affiliation(s)

Shandong Luqiao Group Co., Ltd, Jinan, Shandong, China

Abstract

To provide technical basis for assembly steel girder in incremental launching method, aimed at the problem of assembling steel girder leaded erection line change which is influenced by temperature variation. According to the vertical temperature variation of steel girder measures in situation in this paper, temperature gradient model was fitted, and the influence of angle for assembly steel girder end under different temperature gradient model was investigated. The results show that angle of assembly steel girder end caused by temperature gradient of top and bottom plane was remarkable. Different assembly temperature scope for top and bottom plane of steel girder was suitable to different segments.

Keywords

Bridge Engineering, Assembly Time, Temperature Gradient Difference Model, Steel Box Girder, Incremental Launched Girder

Cite This Paper

Zhansheng Lin, Jin Li, Tongjun Duan, Ranran Hu. Research on Assembly Time for Steel Girder. International Journal of Engineering Technology and Construction (2024), Vol. 5, Issue 1: 1-9. https://doi.org/10.38007/IJETC.2024.050101.

References

[1] Tong M ,Tham L G,Au Fr. Extreme Thermal Loading on Steel Bridge in Tropical Region . Journal of Bridge Engineering, 2002, 7(6): 357-366.

[2] Lee J H. Investigation of Extreme Environmental Conditions and Design Thermal Gradients During Construction for Prestressed Concrete Bridge Girders. Journal Bridge Engineering, 2012,17(3): 547-556.

[3] He Shuanhai. Bridge Structure Theory and Calculation Method(2nd edition). Beijing: China Communications Press,2017.

[4] Hao Chao. Study on the Nonlinear Influence of Temperature on Long-span Steel Cable—stayed Bridge During Construction. Journal of Highway and Transp0rtation Research and Development,2003,20(1): 63-66.

[5] Deng Xiaowei, Shi Xuefei, Ruan Xin. Research of Temperature Load and Analysis of Temperature Effect for Large Span Steel Cable-stayed Bridge. Journal of Shijiazhuang Tiedao University: Natural Science Edition, 2010, 23(3): 57-62.

[6] Pan Weili Cai Shiqiang. Influence of Steel Box Girder Temperature Gradient on Cable-stayed Bridge Construction Control .Shandong Jiaotong Keji,2011(3): 1-3.

[7] Ding Youliang, Wang Xiaojing, Wang Gaoxin, et al. Long-term Temperature Monitoring and Analysis of Steel Box Girders of Pearl River Huangpu Bridge .Journal of Southeast University: Natural Science Edition,2012,42(5):945-949.

[8] Sun Jun, Li Aiqun, Ding Youliang. Observation and Research on Temperature Distribution in Steel Box Girders of Runyang Yangtse River Bridge E. Journal of Highway and Transp0rtati0n Research and Development, 2009, 26(8): 94-98.

[9] Ding Youliang, Wang Gaoxin, Zhou Guangdong, et a1. Thermal Difference Characteristic Analysis of a Flat Steel Box Girder in Long-span Suspension Bridge Based on Long-term Field Measurement Data. China Civil Engineering Journal, 2012, 45(5): l14-125.

[10] Ding Youliang, Wang Gaoxin, Zhou Guangdong, et a1. Life-cycle Simulation Method of Temperature Field of Steel Box Girder for Runyang Cable-stayed Bridge Based on Field Monitoring Data. China Civil Engineering Journal, 2013, 46(5): 129-136.